A storm shelter in Perry goes through the city’s regular building permit. As of October 2026, Perry’s fee schedule lists $10 for a storm shelter, plus the state building code fee and a 50-cent city charge on top of that state fee. The application needs a plot plan drawn to scale, and the permit lapses if work does not start within 60 days.

What the $10 permit asks for
The plot plan shows the exact size of your lot, every building already on it and the spot for the shelter. If the lot corners have no survey pins, the Building Official can ask for a survey by an Oklahoma-registered engineer. Permits are issued at City Hall. The city prefers applications through its online permit portal, and paper forms are still accepted.
Ask the installer to draw the plot plan and file the application. Because of the 60-day rule, the permit should come close to the install date. Ask when it will apply and when its crew can start.
Inspections on morning and afternoon blocks
City Hall books inspections first come, first served, in AM or PM blocks. A request made after 8 am goes to the next business day. If the work is not ready and the city has not been notified, it may add a reinspection fee. The quote should say who books each inspection and who pays a reinspection if the crew is not ready.
Where a yard shelter can sit
In Perry’s R-G residential district, a single-family house keeps a 25-foot front yard, 5-foot side yards and a 20-foot rear yard. In a planned unit development, a shelter can sit in a front or side yard if it stays within 18 inches of the ground. Have the installer check both your zoning and the shelter’s height before drawing the plan.
If the spot you want breaks a setback, the request goes to the Board of Adjustment. As of October 2026, the application costs $100. It requires a certified abstractor’s list of property owners within 300 feet. You must attend the meeting. Ask the installer to confirm whether your chosen spot needs a variance. The city offers GIS maps to builders and contractors, which helps the installer place the shelter on the plan.
Flood zones and below-ground units
Building in a mapped flood hazard area needs a separate floodplain development permit. As of October 2026, the city lists $100 for the application review, $25 for the permit and $25 per inspection. SoonerSafe, the state rebate program, will not pay for a below-ground safe room on a floodplain lot. An above-ground room there can still be eligible. Ask the installer to check the flood map for your address before it prices an in-ground unit.
Noble County’s tornado record
The chart below counts every tornado that touched Noble County, not only Perry. Its two strongest were both F4s. The April 26, 1991 tornado had a 66-mile path. Across its full 35-mile path, the May 3, 1999 tornado killed 2 people and injured 26. None of the county’s tornadoes in 2016–2025 was rated EF3 or stronger. For warnings, follow the National Weather Service and Perry’s Department of Emergency Management.
Shelter options for an older Perry house
ACS estimates count 2,181 housing units in Perry, with only 212 built in 2000 or later. With an older house, compare two places: the garage and the yard. For a below-floor garage shelter or an above-ground safe room, ask how the installer will check the slab. An underground yard shelter depends on the setbacks and the flood map. The types comparison sets them side by side.
Perry homeowners may build on their own lot with the permit and inspections. Wiring for lights or outlets still needs a state-licensed electrician. As of October 2026, Perry’s electrical contractor registration costs $50 a year.
Price and the property tax break
Check which prices below include installation before comparing a garage unit with a yard shelter. A shelter can also lower your tax bill. Up to 100 square feet of a shelter added after January 1, 2002 is exempt from property tax under the Oklahoma Constitution. You claim it with form OTC 905 at the county assessor’s office. To claim it for the current tax year, file by March 15. A change of ownership brings the shelter back onto the taxable property record.
Getting a Perry quote
Use the form below to ask a Perry-area installer for a free quote. Say whether you want the shelter in the garage or the yard. Also say whether your home is in a planned development. For this lot, have the quote spell out:
- a visit to check the proposed shelter location
- the plot plan and permit, filed by the installer
- the $10 shelter fee, state fee and $0.50 city charge itemized
- any floodplain permit your lot needs
- delivery, dirt haul-off and anchoring, each priced separately
Local facts
- Perry requires a building permit before anyone builds, alters or repairs a structure, and the application needs a plot plan drawn to scale showing the lot and where the work goes. Section 5-106 B. Building Permit Required (City of Perry Code of Ordinances)
- A Perry building permit is canceled automatically if work does not start within 60 days of being issued. Section 5-106 D (City of Perry Code of Ordinances)
- Perry inspections are booked through City Hall in morning or afternoon blocks, first come first served, and calls after 8 am go to the next business day. Permits and Inspections — A Note On Scheduling (City of Perry)
- Perry homeowners may do construction work on their own property themselves, as long as they get the required permits and inspections. Section 5-115 B. General Construction (City of Perry Code of Ordinances)
- In a Perry planned development, a detached emergency shelter may sit in a required front or side yard if no part of it rises more than 18 inches above ground. Section 12-296C PUD: Development Guidelines — 3.b.(2) Obstructions In Required Yards (City of Perry Code of Ordinances)
- Half of Perry's 2,181 homes were built in 1965 or earlier, and 74% were built before 1980. American Community Survey 5-year estimates 2020-2024, tables B25034 and B25035 (U.S. Census Bureau)
- NOAA's Storm Prediction Center records 48 tornadoes in Noble County from 1950 through 2025; 2 of them were rated F3/EF3 or stronger. SPC Severe Weather Database: tornadoes 1950-2025 (NOAA Storm Prediction Center)
- 7 of those tornadoes happened in 2016–2025. SPC Severe Weather Database: tornadoes 1950-2025 (NOAA Storm Prediction Center)
- The deadliest tornado on record that touched Noble County was the F4 of May 3, 1999, which killed 2 people along its full path. SPC Severe Weather Database: tornadoes 1950-2025 (NOAA Storm Prediction Center)
Storm shelter prices in Oklahoma
The overall range is $3,000–$15,000.
| Option | Low estimate | High estimate | Notes |
|---|---|---|---|
| Outdoor underground shelter, 6×8 to 7×10 ft, installed | $4,200 | $5,650 | Published 2026 price lists of two Oklahoma installers (Sprague's Backhoe, CM Construction). Digging and installation included; CM Construction does not state the shelter material. |
| Above-ground safe room for 9–16 people, installed | $6,250 | $8,000 | Same two Oklahoma installer price lists. Installation included. |
| Above-ground steel shelter for 4–16 people, unit only | $3,995 | $9,245 | Survive-a-Storm list prices (TwisterPod and Extreme). Installation not included; delivery extra; needs a concrete pad. |
| In-garage underground shelter, installed | $6,000 | $15,000 | National cost guides (HomeGuide, Angi). No Oklahoma installer publishes an installed price for this type. |
| Typical storm shelter project in Oklahoma | $3,000 | $8,000 | Angi's state range, updated September 2026. |
Usually included
- For the Oklahoma installer prices: the shelter, digging and installation (underground) or delivery, setting and anchoring (above-ground)
Often extra
- City permit: $34.50 in Moore, $54.50 in Norman, $88 (indoor) or $132 (outdoor) plus a state fee in Tulsa
- Dirt haul-off and delivery beyond the installer's service area
- A concrete pad for above-ground units, about $5–$10 per square foot (HomeGuide, 2024)
- Anchoring when billed separately, about $200–$350 (HomeGuide, 2024)
Questions to ask a shelter installer
Can you show written proof that this shelter and its door meet ICC 500 and FEMA P-361?
FEMA does not certify products and says a seller's claim of meeting these criteria should be backed by independent testing or engineering. FEMA P-320 (2021)
How will it be anchored, and is my slab strong enough for it?
FEMA notes that many prefabricated safe rooms end up on slabs without enough reinforcement, which undermines the protection they are built for. FEMA P-320 (2021)
Who gets the city permit, and can I see it before work starts?
Oklahoma's Construction Industries Board tells homeowners to see the building permit before letting work begin. Oklahoma CIB, Home Repair Tips
Will you register the shelter with the city, or should I?
FEMA advises registering the exact location of the entrance with local officials right after installation, so rescuers can find it if debris blocks the exit. FEMA P-320 (2021)
For a below-ground unit: is my lot in a flood zone, and how will water be kept out?
ICC 500 does not allow below-ground shelters in mapped flood hazard areas, and FEMA recommends a sump pump inside in-ground units. FEMA P-320 (2021)
If I want the SoonerSafe rebate, should I wait until I am selected?
SoonerSafe does not pay for a shelter installed before you are notified of selection, and the installer has to sign the certificate of installation. SoonerSafe FAQ (Oklahoma Emergency Management)
What is the payment schedule, and how much is due up front?
The FTC advises against paying the full amount up front and against making the final payment before the work is done. FTC, How To Avoid a Home Improvement Scam
Frequently asked questions
How much is a storm shelter permit in Perry?
As of October 2026, Perry's fee schedule lists $10 for a storm shelter. The city also collects the state building code fee and adds 50 cents to it. Ask the installer to itemize these charges in the written quote.
How long is a Perry permit good for?
Work has to start within 60 days after the permit is issued, or the permit is canceled automatically. Ask the installer to apply once the install date is set.
Can a shelter go in my front yard in Perry?
In a planned unit development, a detached emergency shelter may occupy a required front or side yard if it stays within 18 inches of ground level. Have the installer confirm the placement rules for your lot before choosing a location.
Can I install a shelter myself in Perry?
Perry lets homeowners build on their own property with the required permits and inspections. SoonerSafe does not pay for owner-installed safe rooms, though. Use a state-licensed electrician for the shelter's lights or outlets.
Is the SoonerSafe rebate open for Perry homeowners?
Not right now. As of October 2026, Oklahoma Emergency Management says the 2026 program is not open. The published rules cap the rebate at $3,000 and 75% of the cost. A shelter installed before you are selected does not qualify.
Sources
- Section 12-296C PUD: Development Guidelines — 3.b.(2) Obstructions In Required Yards (City of Perry Code of Ordinances)
- Permits and Inspections — A Note On Scheduling (City of Perry)
- Application to be Heard By The Board of Adjustment (City of Perry)
- SoonerSafe Safe Room Rebate Program (Oklahoma Emergency Management)
- SoonerSafe Rules & Regulations (Oklahoma Emergency Management)
- SoonerSafe Frequently Asked Questions (Oklahoma Emergency Management)
- Oklahoma Constitution – Article X – Revenue and Taxation (Oklahoma State Senate)
- OAC 710:10, Chapter 10. Ad Valorem (Oklahoma Tax Commission, 2026 rules)
- Frequently Asked Questions (Oklahoma Construction Industries Board)
- SPC tornado database 1950-2025, all tornadoes (NOAA Storm Prediction Center)
- American Community Survey 5-year estimates 2020-2024, tables B25034 and B25035 (U.S. Census Bureau)
- Oklahoma Below-Ground Storm Shelters (Sprague's Backhoe)
- Oklahoma Above-Ground Storm Shelters (Sprague's Backhoe)
- Storm Shelters (CM Construction)
- Residential Storm Shelters (Survive-a-Storm)
- How Much Does a Storm Shelter Cost? (Angi)
- Tornado & Storm Shelter Costs (HomeGuide)
- SPC Severe Weather Database: tornadoes 1950-2025 (NOAA Storm Prediction Center)